SALIENT
FEATURES OF IS:13920 - 1993.
CODE OF PRACTICE FOR DUCTILE DETAILING OF RC STRUCTURES
SUBJECTED TO SEISMIC FORCES.
COLUMN
DESIGN:
(
Actual program is available in
Super Civil CD ) |
SR |
DESCRIPTION |
1 |
Ductile
detailing is a must for structures in Zone IV & V. However it should
also be followed in zone III, when Importance factor is > 1.0
OR
Structure is > 5.0 Storey high OR the structure is industrial in
nature. |
2 |
If
the factored axial stress under seismic loads are < 0.1 fck,
than ductile detailing requirements are not applicable. |
3 |
B/D
> 0.40 preferably. |
4 |
Width
should not be < 200 MM for span of framing beams up to 5.0 M OR effective
height of column up to 4.0 M, else it should be 300 MM. |
5 |
Lap
splice shall only be allowed in central half of column length. All splice
shall have Ld in tension. |
6 |
Links
shall be provided over the entire splice length at spacing not>150
MM. |
7 |
Not
more than 50 % of bars to be spliced at one section. |
8 |
Spacing
of main longitudinal bars shall not > than 300 MM. Each bar shall
have cross tie. |
9 |
All
links shall be closed type, having a 135° hook with a 10 Ø extension,
but not less than 75 mm at each end. |
10 |
Special
confining reinforcement (SCR)
requirements be met with, unless a larger amount of (links) transverse
reinforcement is required from shear strength consideration. |
11 |
The
length of (SCR) shall
not be less than the following.
Maximum lateral column dimension.
1 ÷ 6 of clear column span (height).
450 MM. |
12 |
The
length of (SCR) shall
be at least 300 MM in foundations. |
13 |
When
the point of contra-flexure is not within middle half of column than
(SCR) shall be provided
for full column height. |
14 |
In
case of column/shear wall discontinuity (SCR)
shall be provided for full height, also it should extend Ld in to the
discontinuity. |
15 |
The
spacing of (SCR) shall
not be more than the following.
1/4 of least column dimension.
100 MM.
However it shall not be < 75 MM. |
16 |
Elsewhere
the spacing of LINKS shall not < 1/2 of least column dimension. |
17 |
Link
spacing shall not be > 300 MM OR 16 Ø. { As per IS-456-2000 }. |
18 |
The
minimum area of link bar shall be :
ASH = 0.18 * SP*H*FCK/FY {AG/AK -1.0}
SP : SPACING OF LINKS.
H : MAXIMUM SPACING OF LONGITUDINAL BAR.
AG : GROSS AREA.
AK = CONCRETE CONFINED CORE AREA. |
19 |
All
joints shall have (SCR)
& ASH as mentioned above. However only 50 % of ASH along with (SCR)
spacing of 150 MM can be provided in following case.
Column having beams from all 4 sides &
Beam width > 3/4 Column width. |
|