ANALYSIS OF RATES OF VARIOUS 
BUILDING ITEMS
( FOLLOWING 63 ITEMS ARE INCLUDED IN SCCD )

EXCAVATION
1 EXCAVATION IN ORDINARY SOIL
2 EXCAVATION IN MURUM
3 EXCAVATION IN SOFT ROCK
4 EXCAVATION IN HARD ROCK
5 RUBBLE SOLING
PLAIN & REINFORCED CONCRETE
6 CONCRETE GRADES M5, M7.5, M10 & M15 ( Large Project + Batching Plant )
7 CONCRETE GRADES M20, M25, M30 & M35 ( Large Project + Batching Plant )
8 CONCRETE GRADE M5 ( General )
9 CONCRETE GRADE M7.5 ( General )
10 CONCRETE GRADE M10 ( General )
11 CONCRETE GRADE M15 IN FOUNDATION ( General )
12 CONCRETE GRADE M15 IN SUPER STRUCTURE BEAMS ( General )
13 CONCRETE GRADE M15 IN SUPER STRUCTURE SLABS ( General )
14 CONCRETE GRADE M15 IN SUPER STRUCTURE COLUMNS ( General )
15 CONCRETE GRADE M15 IN STAIRCASE ( General )
16 CONCRETE GRADE M15 IN PARDI / PARAPET / WALL ( General )
17 CONCRETE GRADE M20 IN FOUNDATION ( General )
18 CONCRETE GRADE M20 IN SUPER STRUCTURE BEAMS ( General )
19 CONCRETE GRADE M20 IN SUPER STRUCTURE SLABS ( General )
20 CONCRETE GRADE M20 IN SUPER STRUCTURE COLUMNS ( General )
21 CONCRETE GRADE M25 IN FOUNDATION ( General )
22 CONCRETE GRADE M25 IN SUPER STRUCTURE BEAMS ( General )
23 CONCRETE GRADE M25 IN SUPER STRUCTURE SLABS ( General )
24 CONCRETE GRADE M25 IN SUPER STRUCTURE COLUMNS ( General )
REINFORCEMENTS
25 REINFORCEMENTS
MASONRY WORKS
26 350 THICK RUBBLE MASONRY
27 230 THICK BRICK MASONRY
28 150 ( 6 " ) THICK BRICK MASONRY
29 115 ( 4 " ) THICK BRICK MASONRY
30 200 THICK HOLLOW BLOCK MASONRY
31 100 THICK HOLLOW BLOCK MASONRY
PLASTER
32 10 THICK NEERU PLASTER
33 15 THICK NEERU PLASTER
34 15 THICK PLAIN PLASTER WITH WATER PROOFING COMPOUND
35 RATE ANALYSIS FOR 20 mm THICK PLAIN PLASTER  WITH WATER PROOFING COMPOUND IN 2 COATS
MORTARS
36 RATE ANALYSIS FOR CEMENT MORTAR CM 1:2
37 RATE ANALYSIS FOR CEMENT MORTAR CM 1:3
38 RATE ANALYSIS FOR CEMENT MORTAR CM 1:4
39 RATE ANALYSIS FOR CEMENT MORTAR CM 1:5
40 RATE ANALYSIS FOR CEMENT MORTAR CM 1:6
41 RATE ANALYSIS FOR LIME MORTAR LM 1:2
42 RATE ANALYSIS FOR LIME MORTAR LM 1:3
43 RATE ANALYSIS FOR LIME MORTAR LM 1:4
44 RATE ANALYSIS FOR LIME MORTAR LM 1:5
45 RATE ANALYSIS FOR LIME MORTAR LM 1:6
FLOORING
46 RATE ANALYSIS FOR 50 mm THICK IPS
47 RATE ANALYSIS FOR MOSAIC FLOORING
48 RATE ANALYSIS FOR MOSAIC TILE SKIRTING
49 RATE ANALYSIS FOR  KOTAH STONE FLOORING
50 RATE ANALYSIS FOR  KOTAH  STONE RISERS & TREADS
51 RATE ANALYSIS FOR  KOTAH  STONE SKIRTING
52 RATE ANALYSIS FOR  GLAZED / CERAMIC TILE FLOORING
53 RATE ANALYSIS FOR  GLAZED DADO
54 RATE ANALYSIS FOR  MARBLE FLOORING
WATER PROOFING
55 RATE ANALYSIS FOR GLAZED CHINA MOSAIC W/P FOR TERRACE
56 RATE ANALYSIS FOR BRICK BAT W/P FOR TERRACE
57 RATE ANALYSIS FOR BRICK BAT W/P FOR TOILET
                                  
Note: 
1. Material cost should include all taxes, such as sales, octroi, excise etc.
2. We have added 5 % as wastage wherever applicable.
3. Rates should include equipments, machineries, temporary approaches, water, fuel & electrical consumptions, contingencies & sundries.
4. Over head should include office expenses, supervision, administration, accounting, insurance, safety / security & storage costs.