DISPLAY OF OPTIMIZED RECORDS
 

Details of Optimization of Steel
------------------------------------------------
Organization : Super Civil CD
Project : 20 Story Bldg.
Project No : 8912
Building ID : Admin
Floor Number : 12
Floor Level : 36.0
Standard Member Length : 12000
File Name : D:\000Optimize_Steel\Example.ops
------------------------------------------------
For MC 125 Section : 

Number of Sets : 1 : Members Marked : 91,91,91,92
Number of Sets : 1 : Members Marked : 92,92,93,93
Number of Sets : 1 : Members Marked : 1,1,1,2
Number of Sets : 1 : Members Marked : 2,2,3,3
Number of Sets : 1 : Members Marked : 3,4,4,4
Number of Sets : 1 : Members Marked : 5,5,5,6
Number of Sets : 1 : Members Marked : 6,6,19,19
Number of Sets : 1 : Members Marked : 19,20,20,20
Number of Sets : 1 : Members Marked : 21,21,21,46
Number of Sets : 1 : Members Marked : 46,46,47,47
Number of Sets : 1 : Members Marked : 47,48,48,48
Number of Sets : 1 : Members Marked : 93

Total Nos. of Std. Length of MC 125 Sec. Required = 12
Total Length of MC 125 Sec. Required = 144 M
Total Weight of MC 125 Sec. = 1828.8 Kg
Total Weight of MC 125 Sec. as per FAB drg. = 1687.07 Kg
Wastage of MC 125 Section = 8.4 %
------------------------------------------------
For MC 150 Section : 

Number of Sets : 1 : Members Marked : 64,64,64,65
Number of Sets : 1 : Members Marked : 65,65,66,66
Number of Sets : 1 : Members Marked : 66,67,67,67
Number of Sets : 1 : Members Marked : 68,68,68,69
Number of Sets : 1 : Members Marked : 69,69,88,88
Number of Sets : 1 : Members Marked : 88,89,89,89
Number of Sets : 1 : Members Marked : 34,35,35,35
Number of Sets : 1 : Members Marked : 40,40,40,41
Number of Sets : 1 : Members Marked : 37,37,38,38
Number of Sets : 1 : Members Marked : 25,25,25,26
Number of Sets : 1 : Members Marked : 26,26,27,27
Number of Sets : 1 : Members Marked : 27,28,28,28
Number of Sets : 1 : Members Marked : 29,29,29,30
Number of Sets : 1 : Members Marked : 30,30,31,31
Number of Sets : 1 : Members Marked : 31,32,32,32
Number of Sets : 1 : Members Marked : 33,33,33,34
Number of Sets : 1 : Members Marked : 34,36,36,36
Number of Sets : 1 : Members Marked : 37,38,39,39
Number of Sets : 1 : Members Marked : 39,41,41,42
Number of Sets : 1 : Members Marked : 50,50,51,51
Number of Sets : 1 : Members Marked : 56,56,56,57
Number of Sets : 1 : Members Marked : 52,52,53,53
Number of Sets : 1 : Members Marked : 58,58,59,59
Number of Sets : 1 : Members Marked : 42,42,49,49
Number of Sets : 1 : Members Marked : 18,49,50,76
Number of Sets : 1 : Members Marked : 51,52,53,54
Number of Sets : 1 : Members Marked : 54,54,55,55
Number of Sets : 1 : Members Marked : 55,57,57,58
Number of Sets : 1 : Members Marked : 59,60,60,60
Number of Sets : 1 : Members Marked : 81,90,90,90
Number of Sets : 1 : Members Marked : 18,18,76,76
Number of Sets : 1 : Members Marked : 17,17,77,77
Number of Sets : 1 : Members Marked : 16,17,77,78
Number of Sets : 1 : Members Marked : 7,7,7
Number of Sets : 1 : Members Marked : 8,8,8
Number of Sets : 1 : Members Marked : 9,9,9
Number of Sets : 1 : Members Marked : 10,10,10
Number of Sets : 1 : Members Marked : 11,11,11
Number of Sets : 1 : Members Marked : 12,12,12
Number of Sets : 1 : Members Marked : 13,13,13
Number of Sets : 1 : Members Marked : 14,14,14
Number of Sets : 1 : Members Marked : 15,15,15
Number of Sets : 1 : Members Marked : 16,16,78,78
Number of Sets : 1 : Members Marked : 79,79,79,80
Number of Sets : 1 : Members Marked : 80,80,81,81

Total Nos. of Std. Length of MC 150 Sec. Required = 45
Total Length of MC 150 Sec. Required = 540 M
Total Weight of MC 150 Sec. = 8856 Kg
Total Weight of MC 150 Sec. as per FAB drg. = 8448.62 Kg
Wastage of MC 150 Section = 4.82 %
------------------------------------------------
For MC 200 Section : 

Number of Sets : 1 : Members Marked : 82,82,82
Number of Sets : 1 : Members Marked : 83,83,83
Number of Sets : 1 : Members Marked : 84,84,84
Number of Sets : 1 : Members Marked : 85,85,85
Number of Sets : 1 : Members Marked : 86,86,86
Number of Sets : 1 : Members Marked : 87,87,87
Number of Sets : 1 : Members Marked : 70,70
Number of Sets : 1 : Members Marked : 70,71
Number of Sets : 1 : Members Marked : 71,71
Number of Sets : 1 : Members Marked : 72,72
Number of Sets : 1 : Members Marked : 72

Total Nos. of Std. Length of MC 200 Sec. Required = 11
Total Length of MC 200 Sec. Required = 132 M
Total Weight of MC 200 Sec. = 2917.2 Kg
Total Weight of MC 200 Sec. as per FAB drg. = 2750.79 Kg
Wastage of MC 200 Section = 6.05 %
------------------------------------------------
For MB 200 Section : 

Number of Sets : 1 : Members Marked : 73,73
Number of Sets : 1 : Members Marked : 73,74
Number of Sets : 1 : Members Marked : 74,74
Number of Sets : 1 : Members Marked : 75,75
Number of Sets : 1 : Members Marked : 75

Total Nos. of Std. Length of MB 200 Sec. Required = 5
Total Length of MB 200 Sec. Required = 60 M
Total Weight of MB 200 Sec. = 1524 Kg
Total Weight of MB 200 Sec. as per FAB drg. = 1332.74 Kg
Wastage of MB 200 Section = 14.35 %
------------------------------------------------
For MB 250 Section : 

Number of Sets : 1 : Members Marked : 61,61
Number of Sets : 1 : Members Marked : 61,62
Number of Sets : 1 : Members Marked : 62,62
Number of Sets : 1 : Members Marked : 63,63
Number of Sets : 1 : Members Marked : 63

Total Nos. of Std. Length of MB 250 Sec. Required = 5
Total Length of MB 250 Sec. Required = 60 M
Total Weight of MB 250 Sec. = 2238 Kg
Total Weight of MB 250 Sec. as per FAB drg. = 1957.13 Kg
Wastage of MB 250 Section = 14.35 %
------------------------------------------------
For MB 350 Section : 

Number of Sets : 1 : Members Marked : 22,22
Number of Sets : 1 : Members Marked : 22,23
Number of Sets : 1 : Members Marked : 23,23
Number of Sets : 1 : Members Marked : 24,24
Number of Sets : 1 : Members Marked : 24,43
Number of Sets : 1 : Members Marked : 43,43
Number of Sets : 1 : Members Marked : 44,44
Number of Sets : 1 : Members Marked : 44,45
Number of Sets : 1 : Members Marked : 45,45

Total Nos. of Std. Length of MB 350 Sec. Required = 9
Total Length of MB 350 Sec. Required = 108 M
Total Weight of MB 350 Sec. = 5659.2 Kg
Total Weight of MB 350 Sec. as per FAB drg. = 5451.7 Kg
Wastage of MB 350 Section = 3.81 %
------------------------------------------------

Total Actual Weight of Steel = 23.023 Ton

Total Theoretical Weight of Steel as per FAB drg. = 21.628 Ton

Total Wastage of Structural Steel = 6.45 %